• The letter of award of work has been issued to INOX Wind Limited on dated 21.11.2014 in the presence of Minister of Railways, Shri Suresh Prabhu, MOSR, Shri Manoj Sinha, Chairman Railway Board and REMCL officials at Railway Board. 

  

  • PPA has been signed between DVC & NCR for ‘Purchasing 50 MW power on short term bilateral arrangement form DVC for three months, extendable to another three months period, on dt 05.02.15.

 

  • All preliminary Formalities completed through exchange for Diwana. The Tri-Partite Agreement (TPA) between NR, REMCL and M/s PTC India Ltd signed on 20.02.2014.

 

  • Locations have been finalized for installation of 157 MW wind power plant.

 

  • Procurement of economical power -150 MW in the state of WB through open bidding process dt. 21.01.15.

 

  • Railways has mandated REMCL for managing & implementing solar energy projects up to 500 MW with VGF Vide letter dt. 30.12.2014.